• Bertha and 1st streets

The 1st and Bertha streets roadway and drainage improvement project work will consist of reconstruction and resurfacing the two roads, installing a new stormwater collection system on Bertha Street and rehabilitation of the existing stormwater collection system on 1st Street. Due to the underground work and full-depth road reconstruction, there will be lane closures and detours for extended periods.

• Marathon

A contractor has begun sidewalk repairs for future ramps and crossings, as well as directional bores for electrical conduits at the intersection of U.S. 1 and Sombrero Beach Road (Mile Marker 50.1) in Marathon. Sidewalk detours will be present for pedestrians and cyclists to follow.

• Channel 5 Bridge

Through Friday, June 18, traffic pacing will occur on the Channel 5 Bridge between 7 a.m. and 5 p.m., while engineers inspect the bridge columns. Law enforcement officers will slow traffic down as needed. Two lanes will remain open, but drivers, bicyclists and pedestrians may experience delays. 

• U.S. 1, Old Seven-Mile Bridge

Bridge rehabilitation project is expected to be completed in February 2022.

• U.S. 1, various locations

Hurricane Irma bridge repairs, roadway, shoulder, shore, path and fencing projects throughout the Keys. Also, various landscape improvement projects.

• Information

For traffic information, consult 511 or 305-849-1847 or go to http://www.fl511.com. For questions, call FDOT at 786-510-3921 or email psummers@mrgmiami.com.